LiveFree planning permission check - an answer for any English property in about 90 seconds
Back to articles
Planning15 min read • Updated Jan 2025

Extension Project Checklist: Step-by-Step Guide

Your complete checklist for planning and building an extension in London. Every step from initial ideas through to moving into your new space.

TL;DR - The Quick Answer

A London extension project runs across six phases and typically takes 10-12 months from start to finish. Initial planning (weeks 1-4) covers budget-setting and permitted development checks, followed by design (weeks 5-12), approvals including an 8-week planning determination period (weeks 13-24), procurement with 3-5 builder tenders (weeks 20-28), and 16+ weeks of construction. Completion requires a building control sign-off, trade certificates, and a 2.5-5% retention period.

Phase 1: Initial Planning (Weeks 1-4)

Define your requirements

What do you need? Extra bedroom, larger kitchen, home office?

Set your budget

Include 15-20% contingency. Consider professional fees, not just build costs.

Check permitted development rights

Use our permitted development checker to see what you can build without planning.

Research local planning constraints

Conservation area? Listed building? Tree preservation orders?

Speak to neighbours

Early communication prevents problems later. Good neighbours make projects easier.

London extension project phases and typical durations
PhaseKey TasksTypical Duration
1. Initial planningBudget, PD check, constraints research, neighbour consultationWeeks 1–4
2. DesignAppoint architect, survey, concept + developed design, D&A statementWeeks 5–12
3. ApprovalsPlanning application (8-week determination), party wall, building regsWeeks 13–24
4. ProcurementTechnical drawings, tender to 3–5 builders, sign contractWeeks 20–28
5. ConstructionGroundworks, superstructure, first fix, plastering, second fix, snaggingWeeks 28–44+
6. CompletionBuilding control sign-off, certificates, retention, insurance updateAfter construction

Source: Mayfair Studio project dataData as of 2025

Start your project with confidence
Our AI assistant can check your property constraints, estimate costs, and tell you if you need planning permission - all in 2 minutes.
Check my property
Free · 2 min · no signup

Phase 2: Design (Weeks 5-12)

Appoint an architect or designer

Get recommendations, review portfolios, compare quotes (3 minimum).

Site survey completed

Measured survey of existing building. May need topographical survey too.

Initial concept designs

Sketch options showing different approaches. Agree on direction before detail.

Developed design

Floor plans, elevations, sections. Enough detail for planning application.

Design & Access Statement (if required)

Written justification for your design. Required for conservation areas.

Phase 3: Planning & Approvals (Weeks 13-24)

Submit planning application (if needed)

£258 fee for householder applications. 8 week determination period.

Or apply for Lawful Development Certificate

£129 fee. Confirms your development is permitted. Good for resale.

Party Wall notices served

If building on or near boundary. 2 months notice before work starts.

Structural engineer appointed

For beam calculations, foundation design, structural drawings.

Building regulations application submitted

Full plans or building notice. Full plans recommended for extensions.

Before submitting your planning application, make sure you understand your property constraints.
Enter your address. We’ll check PD rights, flag constraints, and estimate costs — free, 2 minutes.
Free property check →

Phase 4: Procurement (Weeks 20-28)

Technical drawings completed

Detailed construction drawings for builders to quote from.

Specification document

Written specification of materials, finishes, workmanship standards.

Tender to 3-5 builders

Send identical information. Allow 3-4 weeks for quotes.

Check references and insurance

Visit completed projects. Verify public liability and employer's liability.

Sign building contract

JCT Minor Works or similar. Include scope, price, timeline, payment terms.

Phase 5: Construction (Weeks 28-44+)

Pre-start meeting

Agree programme, access, working hours, site setup, communication.

Groundworks & foundations

Building control inspection at foundation stage before concrete pour.

Superstructure

Walls, steel, roof construction. Multiple building control inspections.

First fix (electrics, plumbing, heating)

Pipes and cables before plastering. Last chance to change positions.

Plastering & second fix

Walls finished, sockets and switches installed, kitchen fitted.

Decoration & snagging

Final finishes. Walk through with builder, create snagging list.

Free planning check
Check your extension project against real planning data
Get a personalised cost estimate
Check if you need planning permission
Understand your property constraints
Start free check
No signup required · 2 minutes

Phase 6: Completion

Building control final inspection

Inspector signs off work. Completion certificate issued.

Collect certificates

Electrical Part P certificate, gas certificate, FENSA for windows.

Final payment (minus retention)

Hold 2.5-5% retention for defects liability period (typically 6-12 months).

O&M manuals and warranties

Operation manuals for appliances, warranties for materials, guarantee certificates.

Update home insurance

Notify insurer of increased floor area and rebuild value.

Store documentation

Keep planning approvals, building control certificate, warranties for resale.

Next steps
Ready to start your extension project?
1.
Run a free property check
Drop in your address and our AI cross-references planning records instantly.
2.
Get your cost estimate
A realistic figure based on your borough and project type.
3.
Talk to us
Packages from £1,295, fixed fee, no surprises.
Start my project

A London extension project runs across six phases and typically takes 10–12 months from start to finish. Allow 4 weeks for initial planning, 8 weeks for design, up to 12 weeks for planning approval, 8 weeks for procurement, and 16+ weeks for construction. Retain 2.5–5% of the build cost until the defects liability period expires.

Frequently Asked Questions

Frequently Asked Questions

How long does an extension project take from start to finish?

A typical London extension takes 10-12 months total: 4 weeks initial planning, 8 weeks design, 12 weeks approvals, 8 weeks procurement, and 16+ weeks construction.

When should I start looking for a builder?

Start your builder search during the planning and approvals phase, typically 4-6 months before you want to start construction. Good builders are booked 2-6 months ahead.

Do I need planning permission for my extension?

Many single-storey rear extensions fall under permitted development and don't need planning permission. Check your PD rights first-if you exceed limits or have constraints (conservation area, listed building), you'll need to apply.

Last updated: January 2025